Obtain a building plan / planning permit (state)

Get a planning permit before building. In Lagos the permit is issued by LASPPPA under the Physical Planning Permit Regulations 2019: land title & survey → architectural and engineering drawings → submission and assessment → processing fee → permit within 28 days; construction is then supervised by LASBCA.

4
steps
4
agencies involved
Who you will deal with
State Lands Bureau / registered surveyorRegistered architect and engineersLagos State Physical Planning Permit Authority (LASPPPA) / state planning authorityLASPPPA; LASBCA
The steps
  1. 1Secure land title and survey
    Agency
    State Lands Bureau / registered surveyor
    What is required
    Establish a registered title (C of O or perfected assignment) and a survey plan for the site. Planning permits are refused without evidence of title and an approved survey.
    Documents
    Title document; survey plan
    Typical timeline
    Precondition
  2. 2Prepare drawings to code
    Agency
    Registered architect and engineers
    What is required
    Prepare architectural drawings, structural and services drawings, and (for larger schemes) soil investigation and structural stability reports, in compliance with the Operative Development Plans, state planning standards and the National Building Code.
    Documents
    Architectural, structural and services drawings; stability report
    Typical timeline
    Design stage
  3. 3Submit, assess and pay the processing fee
    Agency
    Lagos State Physical Planning Permit Authority (LASPPPA) / state planning authority
    What is required
    Submit on the e-Planning Permit portal or at the district office. The processing fee = FEE 1 (building plan assessment: building volume L x B x H x zone rate) + FEE 2 (fencing fees, layout ₦100,000, registration ₦50,000, and LPO at 10% of the building assessment). Payment via the Lagos State payment portal.
    Documents
    Application; drawings; assessed processing fee
    Typical timeline
    Assessment
  4. 4Permit issuance and construction oversight
    Agency
    LASPPPA; LASBCA
    What is required
    Applications are processed and approved within 28 days after final screening and payment of the permit processing fee. Collect the stamped approval, then register with the Lagos State Building Control Agency (LASBCA), which supervises construction stage by stage.
    Documents
    Stamped planning permit; LASBCA registration
    Typical timeline
    Within 28 days

Primary source: https://epp.lagosstate.gov.ng/regulations/REVISED_LASPPPA_REGULATION_2019_1.pdf · confidence: high

Also in construction
Register as a builder (CORBON)

The numbers behind the decision

Knowing the process is half of it. ONYX also tracks the operating environment you are entering — daily grid generation, official FX, state-level input prices and inflation, and sector output — each figure source-linked and dated.

ONYX publishes what the responsible agencies publish, with a link to each source. Requirements, fees and timelines change, and an officer's reading of a rule can differ from the published text. Verify against the linked source before you commit money — this is reference information, not legal advice.

ONYX Data & Intelligence · hello@onyxdata.io